The Innes to DUO story
- The Pratt
- Nov 20
- 1 min read
Our Innes Redevelopment provides the perfect example of what to expect with The Pratt Redevelopment.

Innes/DUO:
Project Timeline
The development team chosen in 2016
Zoning Approval granted in 2019
COVID-related delays, 2020-2021
Relocation began in Spring 2022
CHA residents began to move back December of 2024
All CHA move-backs completed by Summer 2025
Unit Mix:
96 public housing units (1-for-1 replacement)
40 middle-income units
194 market-rate units
Partnership
Chelsea Housing Authority (CHA)
Innes Residence Association (IRA)
Joseph J. Corcoran Company (JJC)
John M. Corcoran & Company (JMC&Co)
Community Amenities
Modern kitchens
Energy-efficient appliances
Fitness center
Community gathering rooms
Bike storage
Landscaped green space
Playground and family-friendly areas





Location
170 Central Ave, near the SL3 Silver Line — connecting residents to
East Boston, Logan Airport, and downtown Boston.
Relocation & Right to Return
All current Innes residents will have the right to return once construction is complete. CHA and JJC will provide full relocation support, including temporary housing assistance and personalized move coordination.